August 2009 Town Notes

Parkway Project

Mr. Orban stated that the Corp of Engineers permit has been approved and construction can begin. This was the final permit needed to begin work. Also, a minor permit amendment for work on the pathway has been submitted.

July 2009 Town Notes

Kiawah Island Parkway and Bike Path Project

Mr. Orban stated that BEC has begun placing conduit, not as fast as the Town would like and has requested that BEC speed up the work so the Town may begin with the Parkway Project. The bridgework is tendered to start in early July and will be done from a barge in the river requiring partial lane closures or road stops. The Town still has not secured a permit from the Army Corps of Engineers. The Town is currently reviewing possible landscaping choices for the project. Landscaping will not begin until the fall.